Grid interconnection queue change tracking
Opportunity at a glance
The problem
Power developers can miss changes to projects they track because updates are spread across grid operators’ files.
Proposed solution
Track material generation and storage queue changes with source-linked history for smaller US developers and diligence teams.
- First buyer
- Independent US power developers
- Market
- United States
- Active generator and storage projects
- ~8,200
In this report
Market snapshot
Search demand
interconnection queue data
View monthly data
| Month | Estimated searches |
|---|---|
| Nov 2025 | 30 |
| Dec 2025 | 20 |
| Jan 2026 | 30 |
| Feb 2026 | 40 |
| Mar 2026 | 40 |
| Apr 2026 | 40 |
| May 2026 | 40 |
| Jun 2026 | 50 |
| Jul 2026 | 20 |
| Aug 2026 | 30 |
| Sept 2026 | 20 |
| Oct 2026 | 30 |
Estimates from Keywords Everywhere using Google Keyword Planner, collected 23 Nov 2026. Terms were selected to compare the specific workflow with adjacent searches. Each chart has its own scale. Search phrases may overlap.
Market facts & figures
~8,200
Active generator and storage projects
United States · end of 2025
Berkeley Lab and GridTracker · Queued Up 2026Context and source details
Transmission connection applications in the study. Distribution projects and loads are outside the dataset.
~2,061 GW
Active queue capacity
United States · end of 2025
Berkeley Lab and GridTracker · Queued Up 2026Context and source details
Adds active generation and storage capacity. The report separately notes that total active volume declined by about 10% from 2024.
Calculation Add the reported generation and storage capacity: 1,312 GW + about 749 GW = about 2,061 GW.
>5 years
Median time to reach operation
Projects built in 2025 · regions with data
Berkeley Lab and GridTracker · Queued Up 2026Context and source details
Time from interconnection request to commercial operation for completed projects, subject to geographic coverage.
Market opportunity
Smaller U.S. power developers and diligence teams tracking projects across multiple grid regions could buy alerts about material queue changes, with links to the relevant source snapshots. The value is quicker review of changes that can affect site or investment decisions. A team already receiving comparable coverage from a data provider has less reason to buy.
Problem and impact
A power developer can miss a new delay, milestone or withdrawal when a grid operator updates its project files. Staff compare new and old files by hand, sometimes with changed project names or status fields. A missed change can leave the team making a decision from an old status.
Research findings
- Berkeley Lab’s annual queue snapshot combines data from more than 50 grid operators. Public operator files and commercial dashboards already make many records discoverable.
- An annual snapshot still cannot show the exact sequence of changes an analyst saw between versions. The narrower use case is a defensible change record for projects and milestones a developer tracks across several sources. Queue size measures proposed projects, without proving the number of teams who need independent alerts or how much they would pay.
- Berkeley Lab and GridTracker · Queued Up 2026
- California ISO · Interconnection data and public queues
- NRG Map · Public queue dashboard
Commercial assessment
Evidence of what changed between reporting snapshots is a distinct use case even when public queue data is already available.
Demand and timing
The US sample shows a measurable adjacent data query. Broader category activity and a backlog support testing an alerts workflow despite lower total capacity year over year.
Why now
A national research snapshot reports a backlog exceeding two terawatts at the end of 2025 and material time to operation among projects that reached it. Active capacity fell from 2024. Operators publish queue reports at different intervals, creating an ongoing coordination burden.
Competition & substitutes
NRG Map offers a public queue view and data aggregation. Grid operators publish source files, and an analyst can build a spreadsheet or script. A paid niche would need versioned source evidence for each change, precise portfolio alerts, and a reliable comparison across two or three selected operators.
Risks & open questions
Public update frequency varies, format changes can break ingestion, and portfolio history can be hard to resolve after transfers. Public dashboards or existing data vendors may already satisfy smaller customers. A queue entry predicts neither a construction start nor a connection date.
What to build first
Start with one public operator and a dated source hash, keep snapshots as permitted by source terms, and normalize stable queue identifiers. Show human-readable changes with timestamps and direct provenance. Report parsers that fail and retain their last successful snapshot instead of interpreting missing rows as withdrawals.
Initial customer workflow
Sell an auditable weekly change log to small generation or storage development teams and their advisers. Track a list of relevant projects across a few grid operators. Save time spent reconciling changed study notes, milestones, withdrawals, and estimated operation dates across public files.